Stevenson High School

Meade provided electrical work for the construction of two new additions to the existing high school.  These additions included tie-ins to existing building structure and services.

SHS Additions

Against the backdrop of a global pandemic, Meade overcame many challenges and obstacles
to start in March 2021 and complete in August 2022, with certification as a LEED Platinum Project.

Phase 1 (5-Month Schedule)

  • Completed a 7000 ft. single story Student Services addition.

Phase 2 (12-Month Schedule)

  • An 85,000 ft. 3-story addition completed while the school was operational.
    The addition included community gathering spaces, an open-turf field, a state-of-the-art training facility, a three-story living wall, sleek new locker rooms, a health café, flexible meeting rooms and 90,000 additional square feet of learning space filled with light and designed with many sustainable factors.
  • The field house and fitness addition roofs will be covered with new solar panels, a green roof, and the living wall uses reclaimed water and filters the air.
  • Meade’s electrical scope included a new 2000A service feed.
    In addition to power and lighting, Meade installed the fire alarm system and area of refuge system.
    Low voltage raceways for voice/data and audio visual systems were also provided by Meade.

Phase 3 (5-Week Schedule)

  • Consisted of new directional bored feeds for the football field lighting and new LED Musco light fixtures installed on existing light poles